NORTH TEXAS TOLLWAY AUTHORITY (NTTA) STATE HIGHWAY 161
PHASE 2 AND 3, IRVING, TX

 
Description:  11.5 Mile loop system in Dallas, TX includes North & Southbound 2.3 mile bridge span over the Trinity River. This North Texas Bridge structure required the use of Epoxy Rebar so GTI Composite Slab Bolster® provided a stronger, more cost effective solution to bar support needs while assuring a zero corrosion liability for project engineers .


Owner:  North Texas Tollway Authority (NTTA) in Joint Venture with TXDOT

Engineer:  North Texas Tollway Authority (NTTA)

Size:  11.5 mile loop system around Dallas, TX including four bridges

Contractor:  Williams Brothers Construction, Houston, TX

RB Supplier:  CMC - ABC Coating

RB Installer:  Indus Construction, LP